Padua Grid BESS Unit 3 — Project Summary

Queue ID
ERCOT-28INR0024
Capacity
201.35 MW
Technology
Battery
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
Padua Grid, LLC
IA Status
Facility Study

Padua Grid BESS Unit 3

ERCOT-28INR0024BetaActiveBatteryERCOTLBNL + Live

201.35 MW storage in Bexar, TX · In queue since March 2024 · Proposed COD May 2026

201.35 MW

Capacity

1

Components

Battery

2y 1m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 2m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-15

Project Details

State

TX

County

Bexar

Region

ERCOT

Developer

Padua Grid, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap #5395 O.W Sommer 138kV

Data Source

LBNL + Live

Linked EIA Plant

Padua 3

EIA Plant ID: 68914

View Plant