Uva Creek Solar
302.16 MW generation in Borden, TX · In queue since February 2024 · Proposed COD August 2028
302.16 MW
Capacity
1
Components
Solar
2y 2m
In Queue
IA Executed
IA Status
Signed Oct 2024
Queue → IA
8 months
IA → COD
3y 10m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-08-25
State
TX
County
Borden
Region
ERCOT
Developer
Grape Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 59905 Faraday - 59900 Long Draw
Data Source
LBNL + Live
Linked EIA Plant
Uva Creek Solar
EIA Plant ID: 68739