Uva Creek Solar — Project Summary

Queue ID
ERCOT-26INR0359
Capacity
302.16 MW
Technology
Solar
Status
active
Location
Borden, TX
Region
ERCOT
Developer
Grape Creek Solar, LLC
IA Status
IA Executed

Uva Creek Solar

ERCOT-26INR0359BetaActiveSolarERCOTLBNL + Live

302.16 MW generation in Borden, TX · In queue since February 2024 · Proposed COD August 2028

302.16 MW

Capacity

1

Components

Solar

2y 2m

In Queue

IA Executed

IA Status

Signed Oct 2024

Interconnection Timeline

Queue → IA

8 months

IA → COD

3y 10m

Total Duration

8 months

Construction75%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 30, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-08-25

Project Details

State

TX

County

Borden

Region

ERCOT

Developer

Grape Creek Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345 kV 59905 Faraday - 59900 Long Draw

Data Source

LBNL + Live

Linked EIA Plant

Uva Creek Solar

EIA Plant ID: 68739

View Plant
No news available for this project.