200 MW BESS planned in Robertson, TX — Electric Reliability Council of Texas, Inc.
200 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
Planned: —
Planned Operation
Coordinates
31.1031, -96.6649
County
Robertson, TX
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Tidwell Prairie II LLC | — | — |
| Owner(s) | Tidwell Prairie II LLC | — | — |
| Status | Planned | — | — |
Tidwell Prairie II is a 200 MW battery energy storage system located in Robertson County, Texas. The plant, identified by the EIA plant code 68425, is owned and operated by Tidwell Prairie II LLC. It consists of a single generator unit utilizing batteries as its primary fuel source, which is categorized as 'MWH' in the data. The facility operates within the Electric Reliability Council of Texas (ERCOT) balancing authority, falling under the Texas Reliability Entity (TRE) NERC region.
Tidwell Prairie II holds a notable position within the Texas energy landscape, ranking as the 114th largest power plant out of 224 in the state. Nationally, it is ranked 292nd out of 514 power plants. The plant's operation and development have garnered some attention, as evidenced by at least one news article related to the industry.
Generated from EIA, GEM, and public data sources
NERC Region
TRE
Balancing Authority
Electric Reliability Council of Texas, Inc.
Grid Voltage
345 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Tidwell Prairie II Batt
No generation data available for this plant.
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Phillips Coal Substation · 138 kV
Substation Distance
0.146 km
Operator
Brazos Electric
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
TDWLPR_1_RN
Pricing Hub
HB_NORTH
Secondary Zone
LZ_NORTH
Location Type
Resource Node
Node Source
Curated node match
Energy Vault, Jupiter Power, advance projects in ERCOT BESS market
Energy Vault acquired a 150MW BESS in Texas. Jupiter Power has entered an agreement to provide 100MW of electricity from a BESS facility.
Last updated 2026-03-26
View all articlesTidwell Prairie III Batt