150 MW Solar under construction in Shelby, TN — Tennessee Valley Authority
150 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
—
Operating Since
Coordinates
35.3094, -89.8665
County
Shelby, TN
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Graceland Solar, LLC | — | — |
| Owner(s) | Graceland Solar, LLC | — | — |
| Status | Under construction | construction | — |
Graceland Solar, LLC is a 150 MW solar photovoltaic power plant located in Shelby County, Tennessee. The plant, owned and operated by Graceland Solar, LLC, utilizes a single generator and fixed-tilt solar tracking technology. It is the third-largest solar plant in Tennessee out of six such plants, and ranks 375th nationally among 639 solar facilities.
The plant operates within the Tennessee Valley Authority balancing authority and the SERC NERC region. Its primary fuel source is the sun. No generation data is available to calculate capacity factor or annual output.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Tennessee Valley Authority
Grid Voltage
345 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.
Mane Street Memphis: Graceland Solar project moves forward, Chamber seeks federal funds
The solar project is an 850-acre project from RWE Renewables in partnership with the Tennessee Valley Authority (TVA).
Mane Street Memphis: Graceland Solar project moves forward, Chamber seeks federal funds
The solar project is an 850-acre project from RWE Renewables in partnership with the Tennessee Valley Authority (TVA).
Mane Street Memphis: Graceland Solar project moves forward, Chamber seeks federal funds
The solar project is an 850-acre project from RWE Renewables in partnership with the Tennessee Valley Authority (TVA).
Mane Street Memphis: Graceland Solar project moves forward, Chamber seeks federal funds
The solar project is an 850-acre project from RWE Renewables in partnership with the Tennessee Valley Authority (TVA).
Last updated 2026-03-26
View all 6 articles