1 MW Solar operating in Fresno, CA — California Independent System Operator
1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2017
Operating Since
Coordinates
36.8897, -119.7370
County
Fresno, CA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Tesla Inc. | Tesla | — |
| Owner(s) | Tesla Inc. | — | — |
| Status | Operating | operating | — |
Clovis North High School is a 1 MW solar photovoltaic power plant located in Fresno County, California. The plant began operating in 2017 and has one generator. It is owned and operated by Tesla Inc. The plant's primary fuel source is solar energy.
The plant operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. In its latest year of reported generation, the plant produced 1,462 MWh of electricity, achieving a capacity factor of 16.6%. The solar array uses a fixed tilt tracking system. Clovis North High School ranks 848 out of 862 power plants in California and 7047 out of 7108 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
California Independent System Operator
Grid Voltage
21 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
WRE - COALINGA (49/120MW)
57 MWh
Latest Month
1.5K MWh
Annual Generation
16.6%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Woodward Substation · 115 kV
Substation Distance
1.384 km
Operator
Pacific Gas and Electric
Coord Source
OSM spatial
Market Position
ISO/RTO Market
CAISO
LMP Node
WOODWARD_1_N005
Pricing Hub
TH_ZP26_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match