400.6 MW Solar planned in Henderson, TX — Electric Reliability Council of Texas, Inc.
400.6 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
Planned: —
Planned Operation
Coordinates
32.2515, -95.9568
County
Henderson, TX
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Vistra Zero LLC | Renewable Energy Ventures | — |
| Owner(s) | Vistra Zero LLC | Vistra | — |
| Status | Planned | announced | — |
The Forest Grove - Dodd solar photovoltaic plant is located in Henderson County, Texas. The plant has a total capacity of 400.6 MW and consists of a single generator. It is owned by Vistra and operated by Vistra Zero LLC. The primary fuel source is solar energy. The solar panels utilize a fixed tilt tracking system.
The plant operates within the Electric Reliability Council of Texas (ERCOT) balancing authority and the TRE NERC region. Forest Grove - Dodd ranks as the 21st largest solar plant in Texas out of 192, and 40th nationally out of 639.
Generated from EIA, GEM, and public data sources
NERC Region
TRE
Balancing Authority
Electric Reliability Council of Texas, Inc.
Grid Voltage
138 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Forest Grove Substation · 345 kV
Substation Distance
< 10 km
Operator
Oncor
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
—
Pricing Hub
HB_NORTH
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.