2 MW Solar operating in Orange, NY — New York Independent System Operator
2 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2019
Operating Since
Coordinates
41.5798, -74.1790
County
Orange, NY
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Grabinski Solar LLC | Grabinski Solar | — |
| Owner(s) | Grabinski Solar LLC | — | — |
| Status | Operating | operating | — |
The Grabinski solar photovoltaic plant is located in Orange County, New York. The plant, owned and operated by Grabinski Solar LLC, began operating in 2019. It has a total capacity of 2 MW consisting of a single generator. The plant's primary fuel source is solar energy.
In its most recent year of operation, the Grabinski plant generated 2,459 MWh of electricity, achieving a capacity factor of 14.0%. The plant operates within the New York Independent System Operator (NYISO) balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In terms of size, the Grabinski plant ranks 598 out of 695 solar plants in New York state and 5314 out of 7108 nationally. The solar array uses a fixed-tilt tracking system.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
New York Independent System Operator
Grid Voltage
13.2 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
0 MWh
Latest Month
2.5K MWh
Annual Generation
14.0%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
E.WALDEN_115_KV_TR_1_REV_LBMP_G
Substation Distance
< 10 km
Coord Source
NYISO direct
Market Position
ISO/RTO Market
NYISO
LMP Node
—
Pricing Hub
NYISO Zone G
Node Source
Shared substation inference
Substation identified. Node ID not yet resolved against ISO roster.