1.6 MW Solar operating in Pima, AZ — Tucson Electric Power Company
1.6 MW
Nameplate Capacity
2
Generators
units
Solar Photovoltaic
Technology
2016
Operating Since
Coordinates
32.3740, -110.9740
County
Pima, AZ
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Luminace Solar Arizona 2, LLC | Luminace Solar Arizona 2 | — |
| Owner(s) | Luminace Solar Arizona 2, LLC | — | — |
| Status | Operating | operating | — |
Canyon Del Oro High School Solar is a 1.6 MW solar photovoltaic power plant located in Pima County, Arizona. The plant began operating in 2016 and consists of two generators utilizing fixed-tilt solar tracking. Luminace Solar Arizona 2, LLC is the owner and operator. The plant's primary fuel source is solar energy.
In the most recent year of data, the plant generated 2,401 MWh of electricity, resulting in a capacity factor of 17.1%. Canyon Del Oro High School Solar operates within the Western Electricity Coordinating Council (WECC) NERC region, and its balancing authority is Tucson Electric Power Company. The plant is ranked as the 77th largest solar facility in Arizona out of 93, and 5670th nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
Tucson Electric Power Company
Grid Voltage
13.8 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
153 MWh
Latest Month
2.4K MWh
Annual Generation
17.1%
Capacity Factor
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.