5 MW Solar operating in Middlesex, MA — ISO New England Inc.
5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2014
Operating Since
Coordinates
42.5818, -71.2536
County
Middlesex, MA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | CD US Solar MT3, LLC | CD US Solar MT3 | — |
| Owner(s) | CD US Solar MT3, LLC | — | — |
| Status | Operating | operating | — |
The Shaffer solar photovoltaic plant is located in Middlesex County, Massachusetts. The plant, which began operating in 2014, has a total capacity of 5 MW and consists of a single generator. It is owned and operated by CD US Solar MT3, LLC. The plant utilizes fixed-tilt solar tracking technology.
Shaffer's latest annual generation was 6,708 MWh, resulting in a capacity factor of 15.3%. The plant is connected to the ISO New England Inc. balancing authority and operates within the Northeast Power Coordinating Council (NPCC) NERC region. Shaffer ranks as the 36th largest solar plant in Massachusetts out of 435, and 2942nd nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
13.2 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
301 MWh
Latest Month
6.7K MWh
Annual Generation
15.3%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Billerica Substation · 115 kV
Substation Distance
2.993 km
Operator
National Grid
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
LD.BILERCA 23 T1 LD
Pricing Hub
.H.INTERNAL_HUB
Node Source
Curated node match