146 MW Wind operating in Atchison, MO — Midcontinent Independent Transmission System Operator, Inc..
146 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2009
Operating Since
Coordinates
40.5553, -95.4525
County
Atchison, MO
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Avangrid Power LLC | Avangrid Renewables | — |
| Owner(s) | Avangrid Power LLC | Avangrid | — |
| Status | Operating | operating | — |
Farmers City Wind LLC is a 146 MW wind power plant located in Atchison County, Missouri. The plant began operating in 2009 and is owned by Avangrid, with Avangrid Power LLC as the operator. It consists of a single generator utilizing onshore wind turbine technology. The facility is connected to the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority within the SERC NERC region.
The plant's wind turbines have a hub height of 78 meters and a rotor diameter of 87 meters. The turbines were manufactured by Gamesa, model G87-2.0. In the most recent year of reported data, Farmers City Wind generated 246,382 MWh, achieving a capacity factor of 19.2%. The plant ranks as the 11th largest wind facility in Missouri out of 11, and 543rd nationally out of 734.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
345 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
22.2K MWh
Latest Month
246.4K MWh
Annual Generation
19.2%
Capacity Factor
No financial data available for this plant.
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
ILLINOIS.HUB
Node Source
OSM spatial match
Red Flag Warning: Atchison; Doniphan; Leavenworth; Atchison; Nodaway; Worth; Gentry; Harrison; Holt; Andrew; De Kalb;
Red Flag Warning issued March 21 at 11:23AM CDT until March 21 at 10:00PM CDT by NWS Kansas City/Pleasant Hill MO
Red Flag Warning: Atchison; Doniphan; Leavenworth; Atchison; Nodaway; Worth; Gentry; Harrison; Holt; Andrew; De Kalb;
Red Flag Warning issued March 21 at 11:23AM CDT until March 21 at 10:00PM CDT by NWS Kansas City/Pleasant Hill MO
Seeing double the solar installations in Oregon | Projects Weekly
Avangrid has energized two solar projects in Wasco County, Oregon, totaling 200 MWac. Plus, Zelestra has expanded its relationship with Meta...
Avangrid switches on 57 MW Camino Solar in California | Projects Weekly
In this edition of Projects Weekly, we highlight Avangrid's newest project in California, plus all the latest solar project news you missed.
Last updated 2026-03-21
View all 10 articles