— Project Summary

Queue ID
WAPA-SN-2024-G2
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
Shasta, CA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryWAPA-SNLBNL

125 MW hybrid in Shasta, CA · In queue since November 2024 · Proposed COD December 2028

125 MW

Capacity

1

Components

Solar

1y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

In Study38%
Queue EntryNov 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

CA

County

Shasta

Region

West

Developer

Utility

WAPA Sierra Nevada

Entity

WAPA-SN

Point of Interconnection

Round Mtn-Cottonwood 230-kV Transmission Line

Data Source

LBNL