— Project Summary

Queue ID
WAPA-SN-2024-G1
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Tehama, CA
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-SNLBNL

200 MW hybrid in Tehama, CA · In queue since September 2024 · Proposed COD December 2028

200 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Pre-Study0%
Queue EntrySep 3, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

CA

County

Tehama

Region

West

Developer

Utility

WAPA Sierra Nevada

Entity

WAPA-SN

Point of Interconnection

Keswick-O'Banion 230 kV Line

Data Source

LBNL

No news available for this project.