— Project Summary

Queue ID
WAPA-SN-2023-G4
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Butte, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryWAPA-SNLBNL

100 MW hybrid in Butte, CA · In queue since August 2023 · Proposed COD March 2028

100 MW

Capacity

1

Components

Solar

2y 7m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 7m

Impact Study25%
Queue EntryAug 22, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

Project Details

State

CA

County

Butte

Region

West

Developer

Utility

WAPA Sierra Nevada

Entity

WAPA-SN

Point of Interconnection

Cottonwood-Roseville 230-kV Transmission Line

Data Source

LBNL

No news available for this project.