— Project Summary

Queue ID
WAPA-RM-2024-G2
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryWAPA-RMLBNL

150 MW hybrid in Weld, CO · In queue since September 2024 · Proposed COD December 2028

150 MW

Capacity

1

Components

Solar

1y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

In Study38%
Queue EntrySep 18, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

LAPT

Entity

WAPA-RM

Point of Interconnection

Archer - Ault 230kV

Data Source

LBNL

No news available for this project.