BetaActiveSolarWAPA-RMLBNL
150 MW generation in Morgan, CO · In queue since March 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 9m
In Study38%
Queue EntryMar 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
CO
County
Morgan
Region
West
Developer
—
Utility
LAPT
Entity
WAPA-RM
Point of Interconnection
Hoyt 115-kV
Data Source
LBNL
No news available for this project.