— Project Summary

Queue ID
WAPA-RM-2023-G7
Capacity
200 MW
Technology
Solar
Status
active
Location
Jackson, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarWAPA-RMLBNL

200 MW generation in Jackson, CO · In queue since July 2023 · Proposed COD December 2026

200 MW

Capacity

1

Components

Solar

2y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 5m

In Study38%
Queue EntryJul 24, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

CO

County

Jackson

Region

West

Developer

Utility

CRCM

Entity

WAPA-RM

Point of Interconnection

345kV Ault-Craig transmission line

Data Source

LBNL

No news available for this project.