— Project Summary

Queue ID
WAPA-RM-2023-G3
Capacity
150 MW
Technology
Solar
Status
active
Location
Albany, WY
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarWAPA-RMLBNL

150 MW generation in Albany, WY · In queue since November 2022 · Proposed COD December 2026

150 MW

Capacity

1

Components

Solar

3y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

In Study38%
Queue EntryNov 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

WY

County

Albany

Region

West

Developer

Utility

LAPT

Entity

WAPA-RM

Point of Interconnection

Northpark - Terry Ranch 230-kV

Data Source

LBNL

No news available for this project.