BetaActiveBatteryWAPA-RMLBNL
90 MW storage in Coconino, AZ · In queue since October 2023 · Proposed COD January 2026
90 MW
Capacity
1
Components
Battery
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 3m
Schedule
3 months past proposed COD
In Study38%
Queue EntryOct 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-09
Project Details
State
AZ
County
Coconino
Region
West
Developer
—
Utility
CRCM
Entity
WAPA-RM
Point of Interconnection
Navajo - Glen Canyon 230kV
Data Source
LBNL
No news available for this project.