400 MW generation in Scotts Bluff, NE · In queue since October 2022 · Proposed COD December 2025
400 MW
Capacity
1
Components
Solar
3y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 2m
Schedule
4 months past proposed COD
In Study38%
Queue EntryOct 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
NE
County
Scotts Bluff
Region
West
Developer
—
Utility
LAPT
Entity
WAPA-RM
Point of Interconnection
Archer - Stegall 230-kV
Data Source
LBNL