BetaActiveSolarWAPA-RMLBNL
80 MW generation in Weld, CO · In queue since May 2022 · Proposed COD May 2025
80 MW
Capacity
1
Components
Solar
3y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3 years
Schedule
10 months past proposed COD
In Study38%
Queue EntryMay 26, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-28
Project Details
State
CO
County
Weld
Region
West
Developer
—
Utility
LAPT
Entity
WAPA-RM
Point of Interconnection
Sand Creek 115-kV Switching Station
Data Source
LBNL
No news available for this project.