BetaActiveSolarWAPA-RMLBNL
765 MW generation in San Juan, NM · In queue since October 2021 · Proposed COD December 2023
765 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 2m
Schedule
27 months past proposed COD
In Study38%
Queue EntryOct 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
NM
County
San Juan
Region
West
Developer
—
Utility
CRCM
Entity
WAPA-RM
Point of Interconnection
Lost Canyon - Shiprock 230-kV
Data Source
LBNL
No news available for this project.