BetaActiveSolarWAPA-RMLBNL
150 MW generation in Weld, CO · In queue since December 2018 · Proposed COD December 2021
150 MW
Capacity
1
Components
Solar
7y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
3 years
Schedule
53 months past proposed COD
In Study38%
Queue EntryDec 12, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
CO
County
Weld
Region
West
Developer
—
Utility
CRCM
Entity
WAPA-RM
Point of Interconnection
Ault 230-kV
Data Source
LBNL
No news available for this project.