— Project Summary

Queue ID
WAPA-RM-2019-G3
Capacity
150 MW
Technology
Solar
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarWAPA-RMLBNL

150 MW generation in Weld, CO · In queue since December 2018 · Proposed COD December 2021

150 MW

Capacity

1

Components

Solar

7y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3 years

Schedule

53 months past proposed COD

In Study38%
Queue EntryDec 12, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-01

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

CRCM

Entity

WAPA-RM

Point of Interconnection

Ault 230-kV

Data Source

LBNL

No news available for this project.