BetaActiveWindWAPA-RMLBNL
252 MW generation in Jackson, CO · In queue since November 2018 · Proposed COD December 2022
252 MW
Capacity
1
Components
Wind
7y 4m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
4y 1m
Schedule
39 months past proposed COD
Construction75%
Queue EntryNov 7, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
CO
County
Jackson
Region
West
Developer
—
Utility
CRCM
Entity
WAPA-RM
Point of Interconnection
Craig - Ault 345-kV
Data Source
LBNL
No news available for this project.