BetaActiveWindWAPA-RMLBNL
130 MW generation in Banner, NE · In queue since January 2017 · Proposed COD September 2020
130 MW
Capacity
1
Components
Wind
9y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 8m
Schedule
67 months past proposed COD
In Study38%
Queue EntryJan 17, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-09-15
Project Details
State
NE
County
Banner
Region
West
Developer
—
Utility
LAPT
Entity
WAPA-RM
Point of Interconnection
Roundtop - Stegall 115-kV
Data Source
LBNL