— Project Summary

Queue ID
WAPA-RM-2008-G9
Capacity
90 MW
Technology
Wind
Status
active
Location
Yuma, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindWAPA-RMLBNL

90 MW generation in Yuma, CO · In queue since March 2008 · Proposed COD October 2019

90 MW

Capacity

1

Components

Wind

18 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

11y 7m

Schedule

79 months past proposed COD

In Study38%
Queue EntryMar 28, 2008

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-10-01

Project Details

State

CO

County

Yuma

Region

West

Developer

Utility

LAPT

Entity

WAPA-RM

Point of Interconnection

Wray Sub. 115-kV

Data Source

LBNL