BetaActiveWindWAPA-RMLBNL
90 MW generation in Yuma, CO · In queue since March 2008 · Proposed COD October 2019
90 MW
Capacity
1
Components
Wind
18 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
11y 7m
Schedule
79 months past proposed COD
In Study38%
Queue EntryMar 28, 2008
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-10-01
Project Details
State
CO
County
Yuma
Region
West
Developer
—
Utility
LAPT
Entity
WAPA-RM
Point of Interconnection
Wray Sub. 115-kV
Data Source
LBNL
No news available for this project.