— Project Summary

Queue ID
WAPA-MPP-2024-MP1
Capacity
500 MW
Technology
Battery
Status
active
Location
Mohave, AZ
Region
West
Developer
IA Status

BetaActiveBatteryWAPA-MPPLBNL

500 MW storage in Mohave, AZ · In queue since January 2024 · Proposed COD December 2028

500 MW

Capacity

1

Components

Battery

2y 2m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 11m

Pre-Study0%
Queue EntryJan 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

AZ

County

Mohave

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-MPP

Point of Interconnection

Mead 500kV Substation

Data Source

LBNL

No news available for this project.