BetaActiveBatteryWAPA-MPPLBNL
500 MW storage in Mohave, AZ · In queue since January 2024 · Proposed COD December 2028
500 MW
Capacity
1
Components
Battery
2y 2m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 11m
Pre-Study0%
Queue EntryJan 5, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-MPP
Point of Interconnection
Mead 500kV Substation
Data Source
LBNL
No news available for this project.