BetaActiveSolarBatteryWAPA-MPPLBNL
600 MW hybrid in Mohave, AZ · In queue since March 2023 · Proposed COD June 2026
600 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntryMar 23, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-23
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-MPP
Point of Interconnection
Mead-Perkins 500kV
Data Source
LBNL
No news available for this project.