BetaActiveSolarBatteryWAPA-MPPLBNL
500 MW hybrid in Yavapai, AZ · In queue since February 2023 · Proposed COD December 2026
500 MW
Capacity
1
Components
Solar
3y 1m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryFeb 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
AZ
County
Yavapai
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-MPP
Point of Interconnection
Mead-Perkins 500kV
Data Source
LBNL
No news available for this project.