BetaActiveWindWAPA-ISLBNL
100 MW generation in Wibaux, MT · In queue since April 2015
100 MW
Capacity
1
Components
Wind
10y 11m
In Queue
In Progress (unknown study)
IA Status
Interconnection Timeline
Total Duration
10y 11m
In Study38%
Queue EntryApr 20, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MT
County
Wibaux
Region
West
Developer
—
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Point of Interconnection
Mingusville 230kV (DC-ME 230kV)
Data Source
LBNL
No news available for this project.