BetaActiveWindWAPA-ISLBNL
250.7 MW generation in Williams, ND · In queue since March 2015
250.7 MW
Capacity
1
Components
Wind
11 years
In Queue
In Progress (unknown study)
IA Status
Interconnection Timeline
Total Duration
11 years
In Study38%
Queue EntryMar 23, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
ND
County
Williams
Region
West
Developer
—
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Point of Interconnection
Williston-Tioga 230kV
Data Source
LBNL
No news available for this project.