BetaActiveWindWAPA-ISLBNL
200 MW generation in Clark, SD · In queue since January 2009
200 MW
Capacity
1
Components
Wind
17y 2m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
17y 2m
Construction75%
Queue EntryJan 22, 2009
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
SD
County
Clark
Region
West
Developer
Crocker Wind
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Point of Interconnection
Groton-Watertown 345kV
Data Source
LBNL
No news available for this project.