BetaActiveGasWAPA-DSWLBNL
50 MW generation in Mohave, AZ · In queue since August 2024 · Proposed COD March 2027
50 MW
Capacity
1
Components
Gas
1y 7m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 7m
Pre-Study0%
Queue EntryAug 23, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Griffith Switchyard 230kV
Data Source
LBNL
No news available for this project.