— Project Summary

Queue ID
WAPA-DSW-2024-G5
Capacity
300 MW
Technology
Wind
Status
active
Location
Mohave, AZ
Region
West
Developer
IA Status

BetaActiveWindWAPA-DSWLBNL

300 MW generation in Mohave, AZ · In queue since August 2024 · Proposed COD December 2029

300 MW

Capacity

1

Components

Wind

1y 7m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 4m

Pre-Study0%
Queue EntryAug 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Project Details

State

AZ

County

Mohave

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Mead _x0013_ Peacock 345kV

Data Source

LBNL

No news available for this project.