BetaActiveGasWAPA-DSWLBNL
200 MW generation in Mohave, AZ · In queue since February 2024 · Proposed COD October 2027
200 MW
Capacity
1
Components
Gas
2y 1m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryFeb 7, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-15
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Griffith Switchyard 230kV
Data Source
LBNL
No news available for this project.