BetaActiveSolarBatteryWAPA-DSWLBNL
250 MW hybrid in La Paz, AZ · In queue since July 2023 · Proposed COD April 2027
250 MW
Capacity
1
Components
Solar
2y 8m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
AZ
County
La Paz
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Bouse 230kV Substation
Data Source
LBNL
No news available for this project.