BetaActiveSolarBatteryWAPA-DSWLBNL
150 MW hybrid in Mohave, AZ · In queue since May 2023 · Proposed COD January 2027
150 MW
Capacity
1
Components
Solar
2y 10m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryMay 2, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-15
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
White Hills _x0013_ Peacock 345kV
Data Source
LBNL
No news available for this project.