— Project Summary

Queue ID
WAPA-DSW-2023-G4
Capacity
225 MW
Technology
Solar+Battery
Status
active
Location
Mohave, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

225 MW hybrid in Mohave, AZ · In queue since April 2023 · Proposed COD December 2026

225 MW

Capacity

1

Components

Solar

2y 11m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntryApr 24, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-30

Project Details

State

AZ

County

Mohave

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

White Hills 345- kV Substation

Data Source

LBNL

No news available for this project.