— Project Summary

Queue ID
WAPA-DSW-2023-G2
Capacity
90 MW
Technology
Gas
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveGasWAPA-DSWLBNL

90 MW generation in Pinal, AZ · In queue since January 2023 · Proposed COD May 2024

90 MW

Capacity

1

Components

Gas

3y 2m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 4m

Schedule

23 months past proposed COD

Pre-Study0%
Queue EntryJan 12, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-01

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Coolidge _x0013_ Sundance 230kV

Data Source

LBNL