BetaActiveGasWAPA-DSWLBNL
90 MW generation in Pinal, AZ · In queue since January 2023 · Proposed COD May 2024
90 MW
Capacity
1
Components
Gas
3y 2m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 4m
Schedule
23 months past proposed COD
Pre-Study0%
Queue EntryJan 12, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Coolidge _x0013_ Sundance 230kV
Data Source
LBNL