— Project Summary

Queue ID
WAPA-DSW-2023-G17
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Mohave, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

300 MW hybrid in Mohave, AZ · In queue since December 2023 · Proposed COD December 2027

300 MW

Capacity

1

Components

Solar

2y 3m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryDec 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

AZ

County

Mohave

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Peacock 345kV Substation

Data Source

LBNL

No news available for this project.