BetaActiveSolarBatteryWAPA-DSWLBNL
300 MW hybrid in Mohave, AZ · In queue since December 2023 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
2y 3m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryDec 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Peacock 345kV Substation
Data Source
LBNL
No news available for this project.