— Project Summary

Queue ID
WAPA-DSW-2023-G15
Capacity
500 MW
Technology
Battery
Status
active
Location
Mohave, AZ
Region
West
Developer
IA Status

BetaActiveBatteryWAPA-DSWLBNL

500 MW storage in Mohave, AZ · In queue since December 2023 · Proposed COD December 2028

500 MW

Capacity

1

Components

Battery

2y 3m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

Pre-Study0%
Queue EntryDec 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

AZ

County

Mohave

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Mead 230kV Substation

Data Source

LBNL

No news available for this project.