25 MW hybrid in Mohave, AZ · In queue since September 2023 · Proposed COD December 2026
25 MW
Capacity
1
Components
Solar
2y 6m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntrySep 5, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
AZ
County
Mohave
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Griffith Switchyard 230kV
Data Source
LBNL