— Project Summary

Queue ID
WAPA-DSW-2023-G11
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Cochise, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

300 MW hybrid in Cochise, AZ · In queue since August 2023 · Proposed COD December 2028

300 MW

Capacity

1

Components

Solar

2y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 4m

Pre-Study0%
Queue EntryAug 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-30

Project Details

State

AZ

County

Cochise

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Apache _x0013_ Adams Tap 115kV

Data Source

LBNL