— Project Summary

Queue ID
WAPA-DSW-2022-G9
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

300 MW hybrid in Pinal, AZ · In queue since July 2022 · Proposed COD December 2025

300 MW

Capacity

1

Components

Solar

3y 8m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 5m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryJul 5, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Test Track 230kV Substation

Data Source

LBNL