— Project Summary

Queue ID
WAPA-DSW-2022-G12
Capacity
380 MW
Technology
Solar+Battery
Status
active
Location
La Paz, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

380 MW hybrid in La Paz, AZ · In queue since November 2022 · Proposed COD May 2026

380 MW

Capacity

1

Components

Solar

3y 4m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Pre-Study0%
Queue EntryNov 17, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-01

Project Details

State

AZ

County

La Paz

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Eagle Eye Substation 230kV

Data Source

LBNL

No news available for this project.