BetaActiveSolarBatteryWAPA-DSWLBNL
380 MW hybrid in La Paz, AZ · In queue since November 2022 · Proposed COD May 2026
380 MW
Capacity
1
Components
Solar
3y 4m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryNov 17, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
AZ
County
La Paz
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Eagle Eye Substation 230kV
Data Source
LBNL
No news available for this project.