BetaActiveSolarBatteryWAPA-DSWLBNL
350 MW hybrid in Maricopa, AZ · In queue since August 2022 · Proposed COD June 2025
350 MW
Capacity
1
Components
Solar
3y 7m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 10m
Schedule
10 months past proposed COD
Pre-Study0%
Queue EntryAug 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Harcuvar 230kV Substation
Data Source
LBNL
No news available for this project.