— Project Summary

Queue ID
WAPA-DSW-2022-G11
Capacity
350 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

350 MW hybrid in Maricopa, AZ · In queue since August 2022 · Proposed COD June 2025

350 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 10m

Schedule

10 months past proposed COD

Pre-Study0%
Queue EntryAug 11, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Harcuvar 230kV Substation

Data Source

LBNL