150 MW hybrid in Pinal, AZ · In queue since July 2022 · Proposed COD November 2025
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 4m
Schedule
4 months past proposed COD
Pre-Study0%
Queue EntryJul 8, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-20
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
ED5 Substation
Data Source
LBNL