— Project Summary

Queue ID
WAPA-DSW-2022-G1
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
La Paz, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

250 MW hybrid in La Paz, AZ · In queue since January 2022 · Proposed COD April 2025

250 MW

Capacity

1

Components

Solar

4y 2m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 3m

Schedule

12 months past proposed COD

Pre-Study0%
Queue EntryJan 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-01

Project Details

State

AZ

County

La Paz

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

Bouse Substation 161kV

Data Source

LBNL