BetaActiveWindWAPA-DSWLBNL
135 MW generation in Yavapai, AZ · In queue since June 2021 · Proposed COD September 2025
135 MW
Capacity
1
Components
Wind
4y 9m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 3m
Schedule
6 months past proposed COD
Pre-Study0%
Queue EntryJun 18, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-30
Project Details
State
AZ
County
Yavapai
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Round Valley _x0013_ Prescott 230-kV Line
Data Source
LBNL