— Project Summary

Queue ID
WAPA-DSW-2021-G4
Capacity
462.5 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryWAPA-DSWLBNL

462.5 MW hybrid in Pinal, AZ · In queue since April 2021 · Proposed COD July 2023

462.5 MW

Capacity

1

Components

Solar

4y 11m

In Queue

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 3m

Schedule

33 months past proposed COD

Pre-Study0%
Queue EntryApr 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-07-01

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Point of Interconnection

ED5 Substation

Data Source

LBNL

No news available for this project.