BetaActiveSolarBatteryWAPA-DSWLBNL
462.5 MW hybrid in Pinal, AZ · In queue since April 2021 · Proposed COD July 2023
462.5 MW
Capacity
1
Components
Solar
4y 11m
In Queue
—
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 3m
Schedule
33 months past proposed COD
Pre-Study0%
Queue EntryApr 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-07-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
ED5 Substation
Data Source
LBNL