BetaActiveSolarBatteryWAPA-DSWLBNL
22 MW hybrid in La Paz, AZ · In queue since March 2021 · Proposed COD December 2022
22 MW
Capacity
1
Components
Solar
5 years
In Queue
—
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 9m
Schedule
40 months past proposed COD
Pre-Study0%
Queue EntryMar 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-01
Project Details
State
AZ
County
La Paz
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Harcuvar-Little Harquahala
Data Source
LBNL
No news available for this project.